|
Date of Meeting
|
Agenda Topics
|
6 May, 2003 |
Signals Project - Goals
and Milestones for Phase I, LHC Test Benches,
AB/CO/IN support for Test Benches |
18th February, 2003 |
GPRS Tests,
Reports from Signals Working Group |
28th January, 2003 |
QRL Review, QRL Controls/Communications
Issues, AB-CO Responsibilities, QRL Controls Coordination/Scheduling
and Issues |
3rd December,
2002 |
Introduction to the IT-CS Group, Accelerator
Network Upgrade Project, LHC Network Configuration, Real Time,
Status Report on the Test Bench in SM18 |
19th November,
2002 |
LTI Project Status and Major Milestones,
LTI Controls in AB-CO, LTI Controls Technical Coordination |
22nd October,
2002 |
Accelerator Timing Strategy |
8th October,
2002 |
Control Room Software for TT40 and
TI8 |
16th, July
2002 |
Experience from RF Test Stands, QRL
Planning Baseline |
2nd, July
2002 |
FGC Gateways, QPS Controls Requirements,
Controls for Machine Interlocks |
18th, June
2002 |
Time Stamping |
4th June,
2002 |
Cost to Completion Budgets LHC-IAS
& SL-CO, Communications Infrastructure, TI 8 Planning |
14th May,
2002 |
QRL Controls : Technical Services,
LHC Alarm System |
5th March,
2002 |
Central Control Support, Control Cables
Requests, Status of Post-Mortem Work |
18th December,
2001 |
Functional Spec. for LHC Front Ends,
Requirements for Analog Signals |
4th December,
2001 |
Status of Real Time Controls, Data
required for LHC Operation |
20th November, 2001 |
Back Ends for LHC, Radiation Monitoring
System for Environment and Surveys, Project Middleware |
23rd October,
2001 |
Timing Functional Specification,
QRL Planning |
9th October,
2001 |
Components Work, Machine Protection
and Control, Post Mortem system |
11th September,
2001 |
Alarm System Preliminary Requirements,
Installation Databases |
17th July,
2001 |
Role of TCR, Front End Architectures |
28th June,
2001 |
Planning for the QRL Controls, Database
Forum, Role of the TCR |
29th May,
2001 |
Slow Timing and Time Stamping for
the LHC, Post Mortem, Planning for the QRL Controls |
24th April,
2001 |
Components Sub-Project Report, Review
of the Alarm Sub-Project Mandate, Demonstration of the SPS 2001
Vertical Size |
13th March,
2001 |
Feedback EDMS tree, LAWG sub-project
progress report, tentative planning for QRL reception tests |
20th February,
2001 |
Controls during sector test, LHC alarms
sub-project status report |
6th February,
2001 |
The PS/SPS NAOS system, What data
is required to understand failures during LHC operation, EDMS
tree for project management |
19th December,
2000 |
Controls news, Middleware, Control
activities of LHC/ICP |
5th December,
2000 |
Controls news, Function generation
in LEP, TCR Data Server (TDS) naming convention, Cryo naming
convention, LHC naming convention |
7th November,
2000 |
Controls news, Industrial components
: review and proposal, SL/PO : function generators |
10th October,
2000 |
Activities of EST/ISS, Planning questionnaire,
SP/OP function generators |
26th September,2000
|
Mandate for LHC Analysis WG, Database
Activities |
12th September,2000
|
Mandate for LHC Alarm Services, Activities
of SL/CO |
20th June,
2000 |
Purpose of LHC-CP meetings. control
of vacuum, future Front End Systems |
7th June, 2000
|
Mandate of LHC-CP, Review of Goals
for 2000, Topics for Future Meetings |
|
|